Dependency Model

What must happen for this project to deliver, and which single failure kills the date.

Assumptions

Everything the model believes, stated before the math. If you do not buy one of these, do not buy the output.

  1. A dependency is only real when evidence binds it. An assumed dependency is labeled INFERRED and never silently upgraded.
  2. The graph is a series system: every gating edge must complete for the project to deliver on time.
  3. Edges carry completion-probability profiles built from an evidence state (complete / in progress / not started / unknown) and a versioned empirical base rate per dependency type.
  4. Dependencies inside a correlation group (same utility, same supplier, same node) fail together: their joint contribution is one shared multiplier, never the product of independent probabilities.
  5. Base-rate priors are policy-versioned placeholders until outcome history re-estimates them; until then the bands are wide and labeled.

Derivation

Each edge gets a per-quarter completion profile. An in-flight edge completes at its type's base quarterly rate q_type; a not-started edge burns its first quarter at half rate. A printed expected-completion date (evidence-bound) concentrates mass to at least 45% in the quarter it falls due. The cumulative profile is:

The joint completion profile is the series product over independent edges, with each correlation group contributing a single factor - the geometric mean of its members, not their product:

The critical dependency is the edge on the longest evidence-adjusted duration chain; slack is the float between an edge's earliest achievable completion and the date its successor needs it. Sensitivity is one-at-a-time toggling: each edge is forced complete in turn and the change in P(deliver on time) is ranked as a tornado.

Current versioned priors (per dependency type, quarterly base completion / expected remaining quarters): transmission upgrade 0.08 / 10; interconnection agreement 0.10 / 8; transformer delivery 0.10 / 8; equipment delivery 0.12 / 6; permit 0.18 / 4; water 0.18 / 4; fiber 0.22 / 3; construction 0.12 / 6; financing 0.22 / 3; generation supply 0.10 / 8; other 0.15 / 5.

Identification strategy

Why the estimate supports the claimed meaning - and where the model refuses to claim more than the data carries.

  • The series form is the identification statement: the project delivers only when every gating edge completes, so the joint is a product (with grouped edges sharing one factor), never an average. Averaging would manufacture on-time probability the graph does not contain.
  • Correlation groups are identified from the record (shared utility, supplier, node), and the shared-multiplier rule is what keeps one utility delay from being priced as several independent risks - or, worse, several independent chances of rescue.
  • Expected-completion dates only bind when they are evidence-bound on the record; a marketing date in prose does not move the profile.

Inputs and outputs

Reads

Dependency graph
Spec Section 33: edges typed by dependency type, status, correlation group, expected completion, needed-by
Milestone states
Project State Model (M01)
Utility and supplier evidence
Evidence graph (spec Sections 29-32)

Writes

  • Critical dependency; per-edge completion profiles
  • Joint completion profile by quarter (consumed by the Delivery Model as the gate)
  • Slack per dependency in quarters
  • Sensitivity tornado: impact of each edge on P(deliver on time)
  • Correlation groups with joint probabilities; correlated failure risk

Calibration and gate evidence

Validation design

  • Edge base rates are re-estimated from outcomes as history accrues; until then the bands are wide and labeled.
  • Correlation groups are validated on resolved multi-project failures - one utility delay hitting several projects at once.

Evidence on record

  • Re-estimation has not yet run in the sealed source; the priors are the versioned placeholders above, explicitly labeled as policy pending outcome history.

Failure modes

The ways this model declines, degrades or goes UNKNOWN - and what it prints when it does.

  • No evidence-bound edges: the Delivery gate is absent and downstream models are told the answer is ungated (upside-biased).
  • Unknown edge status: treated as not-started (the conservative reading), never as complete.
  • Missing expected-completion date: the edge runs on its type base rate only - no mass is concentrated around an unstated date.
  • Dependency type outside the versioned table: falls to the 'other' prior (0.15 / 5) rather than a guess.

Sensitivity

  • The joint profile is most sensitive to the slowest edges: one 10-quarter transmission upgrade dominates the gate until its profile rises.
  • Correlation grouping can move the joint materially on grouped books: three grouped edges at 0.5 contribute 0.5 (geometric mean), not 0.125 (independent product) - the rule raises joint probability where risks move together and removes false diversification.
  • Base-rate priors are the largest open sensitivity: they are policy placeholders, and the page of record says so until outcomes re-estimate them.

Iron rules

A dependency is only real when evidence binds it. An assumed dependency is labeled INFERRED.

Source and audit

Written from the sealed model source. Every run is recorded - model version, frozen inputs, input hash, timestamp. There is no unrecorded model execution.