M2

Delivery Model

When will this project actually deliver, and how much.

Assumptions

Everything the model believes, stated before the math. If you do not buy one of these, do not buy the output.

  1. Delivery is a time-to-event process on quarterly intervals; cancellation is a competing risk with its own empirical hazard.
  2. Projects in the same class share a baseline hazard, estimated non-parametrically from resolved outcomes (Kaplan-Meier).
  3. A sponsor's history moves their projects' hazard through a single multiplier, shrunk toward the sector base rate when the sponsor's sample is thin (Resolution Tracking Model).
  4. Dependencies gate delivery as a series system: the delivery mass in a quarter is scaled by the joint probability that every gating dependency has completed by then (Dependency Model).
  5. Delivered MW convolves the COD distribution with the empirical capacity-attainment ratio (delivered / promised MW) from outcomes.
  6. Where class outcome history is thin (fewer than 10 resolved projects), the model does not pretend to know the baseline: it runs on a labeled wide prior and the distribution reads wide.

Derivation

The baseline delivery hazard per project class is the Kaplan-Meier hazard over resolved outcomes. With d_t deliveries and n_t projects still at risk in quarter t:

The project-level hazard multiplies the baseline by the sponsor multiplier m_s (shrunk per Resolution Tracking), capped at 1:

Delivery and cancellation are competing risks. The discrete mass of delivery in quarter t survives both hazards up to t and then fires the delivery hazard:

Each quarter's delivery mass is then gated by the dependency joint completion profile G(t) - the probability every evidence-bound dependency has completed by t (a series system; correlated members share one multiplier, never a product of independents):

P10 / P50 / P90 read off the CDF. Expected delivered MW multiplies the CDF by promised MW and the mean attainment ratio from outcomes. The delay distribution re-bases the COD mass against the promised COD; cancellation probability is the total cancel mass over the horizon.

Thin-history fallback: below 10 resolved class outcomes the baseline is replaced by a wide prior hazard (6% per quarter delivery, 1.5% cancellation), the output is flagged widePrior, confidence drops to LOW, and the notes say why.

Identification strategy

Why the estimate supports the claimed meaning - and where the model refuses to claim more than the data carries.

  • The baseline is identified from resolved outcomes only - projects that actually delivered or died. In-flight projects contribute nothing, so the hazard cannot be contaminated by projects that merely look healthy today.
  • The sponsor multiplier is identified from the sponsor's own resolved record, shrunk toward the sector base rate at weight n/(n+K): a sponsor with three resolved projects is half-shrunk. Thin sponsors cannot manufacture a good multiplier from a small sample.
  • The dependency gate is identified from evidence-bound edges only. An assumed dependency is labeled INFERRED and the gate is the series joint of what the record actually binds - the model never gates on a dependency nobody documented.
  • The output is always the full distribution. A single-date answer would claim identification the data does not support; the P10-P90 spread is the honest statement of what the class history can pin down.

Inputs and outputs

Reads

Outcomes
Resolved project history per class (spec Section 40): resolution, announced and actual dates, promised and delivered MW
Sponsor track record
Resolution Tracking Model (M15): sponsor hazard multiplier with shrinkage
Dependency graph
Dependency Model (M04): joint completion profile per quarter (spec Section 33)
Project record
Promised MW, promised COD, project class

Writes

  • COD probability mass and CDF by quarter; P10 / P50 / P90
  • Expected delivered MW by date (P50 path)
  • Delay distribution relative to promised COD (P10 / P50 / P90 quarters) and expected delay
  • Probability of partial delivery, probability of cancellation, probability of delivery by promised COD
  • Sponsor multiplier applied; dependency gate profile; confidence grade; wide-prior flag

Calibration and gate evidence

Validation design

  • Rolling-origin backtest against outcomes: every resolved project is predicted from its announcement-date evidence and scored - Brier and log score on resolution, interval coverage on COD.
  • The reliability diagram must sit near the diagonal on resolved history before any customer sees a narrow distribution.

Evidence on record

  • Backtest results are not yet published in the sealed source. The scoring harness and the wide-prior behavior are coded and gated; the score ledger accrues as predictions resolve.

Failure modes

The ways this model declines, degrades or goes UNKNOWN - and what it prints when it does.

  • Project not in the graph: every output UNKNOWN, confidence LOW.
  • Thin class history (n < 10): wide prior, widePrior flag set, confidence LOW, note printed - the model refuses to look precise on thin data.
  • No promised COD on record: delay distribution, expected delay and P(delivered by promised COD) are UNKNOWN.
  • No promised MW on record: delivered-MW path is UNKNOWN.
  • No evidence-bound dependency graph: delivery is ungated and the notes say the answer is upside-biased.

Sensitivity

  • The sponsor multiplier moves the whole hazard path proportionally; a sponsor at 2x base-rate hazard roughly doubles early-quarter delivery mass while history says so.
  • The dependency gate is the binding constraint on late quarters: an edge with a 10-quarter expected duration suppresses COD mass until its completion profile rises.
  • The wide prior (6% quarterly) is the dominant sensitivity on thin classes: the answer is wide because the prior is wide, and the page of record says so.

Iron rules

The output is always a distribution with confidence attached, never a single date.

Source and audit

Written from the sealed model source. Every run is recorded - model version, frozen inputs, input hash, timestamp. There is no unrecorded model execution.